Construction Manager at Risk

Various key characteristics of CM@Risk include: there are separate contracts for design services and for construction services; the contract for construction services may be entered into at the same time as the contract for design services, or at a later time; design and construction of the project may be in sequential phases or concurrent phases; […]

Commissioning

A building has successfully gone through the commissioning process when its equipment and systems have been examined and tested to perform as designed, and its operators have been trained to operate the systems and equipment properly. Lawrence Berkeley National Laboratory cites Hasl and Heinemeier’s “California Commissioning Guide: New Buildings” as an authoritative source. AEC recommends […]

Geo-referencing

A BIM is said to be geo-referenced when the BIM is located with respect to one of the standard geographic survey coordinate grids established to represent locations on the Earth’s surface, such as World Coordinate System 1984 (WCS84)[1] [1] The Massachusetts Port Authority, 2015. BIM Guidelines for Vertical and Horizontal Construction.

Integrated Project Delivery

Integrated Project Delivery (IPD) is a collaboration of all parties, systems and practices to optimize and maximize project success. Defined by the American Institute of Architects, IPD is typically applied to design and construction projects. NOTE: True IPD employs various constructs some of which MPA may be precluded from using by Commonwealth law (such as […]

Integrated Workplace Management System

Integrated Workplace Management System. Such systems incorporate powerful database capabilities to capture enterprise-level functions and serve as decision support tools at all organizational levels and throughout the whole building lifecycle. An IWMS thus reaches into all organizational databases to feed its enterprise-level analyses. [1] [1] The Massachusetts Port Authority, 2015. BIM Guidelines for Vertical and […]

Last Planner®

The person or group that makes assignments to direct workers. Project Architect and ‘discipline lead’ are common names for last planners in design processes. ‘Superintendent’ or ‘foremen’ are common names for last planners in construction processes. [1] [1] The Massachusetts Port Authority, 2015. BIM Guidelines for Vertical and Horizontal Construction.

Last Planner System®

The collaborative, commitment-based planning system that integrates “should-canwill-did planning” (pull planning, make-ready look-ahead planning with constraint analysis, weekly work planning based upon reliable promises, and learning based upon analysis of Percentage of Plan (or Promises) Completed (PPC) and Reasons for Variance [1] [1] The Massachusetts Port Authority, 2015. BIM Guidelines for Vertical and Horizontal Construction.

Lean Project Delivery System

An organized implementation of Lean Principles and Tools combined to allow a team to operate in unison.[1] [1] The Massachusetts Port Authority, 2015. BIM Guidelines for Vertical and Horizontal Construction.

Look Ahead Plan

A short interval plan, based on the pull/phase plan, that identifies all the activities to be performed in the next 6 (or other) weeks. The 6W Look-Ahead Schedule (LAS) is updated each week – always identifying new activities coming 6 weeks out so that the project management team can make appropriate arrangements to assure that […]

Master Schedule

The purpose of a project schedule is to define how the project should be delivered and maintained based on the available resources. The development of a timetable is the first step in project planning. A project schedule shall also be used to provide the status of the project. [1] A schedule that identifies major events […]