CDE state

ELI5-S1: BIM Basics E5: CDE areas and states This term replaces the ‘CDE area’ PAS 1192 term, the idea is the location of the information (container) is not important but its state. Area and section imply moving information from one place to another. This is not necessary in a CDE.

CDE gate

Transition [ISO19650] Transition is used to denote change (in the state of the information container)

file

Equivalent to ISO 19650 term ‘information container’

Document

Equivalent to the term ‘Information container’

information container

ELI5-S1 BIM Basics E12_Information Container explained A persistent set of information retrievable from within a file, system, or application storage hierarchy. [1] named persistent set of information retrievable from within a file, system or application storage hierarchy[SOURCE: BS EN ISO 19650-1:2018, 3.3.12] EXAMPLE: Including sub-directory, information file (including model, document, table, schedule), or distinct sub-set […]

Contract

Appointment ISO 19650 introduce term Appointment to be used instead of the more generic term contract. This means one term can be used for both external contracts and internal work instructions

Appointment

Equivalent to PAS1192 term ‘Contract’ The more generic term appointment has been used in ISO 19650 instead of contract. This means one term can be used for both external contracts and internal work instructions

Employer

Appointing party ISO 19650 term depends on where in the hierarchy the employer is located.The BS EN ISO 19650‑2 appointing party (A) is the equivalent of the PAS 1192‑2:2013 top‑level employer Lead Appointed party (Tier 1) Lead appointed party is not the same as design lead or construction lead in PAS 1192‑2. See 9.5.4.The BS […]

Appointing party

Appointing party term introduced in BS EN ISO 19650 it is meant to replace PAS 1192 term ‘Employer’ ISO 19650 term depends on where in the hierarchy the employer is located.The BS EN ISO 19650‑2 appointing party (A) is the equivalent of the PAS 1192‑2:2013 top‑level employer Who is an Appointing party? Technically speaking an […]

Tier 1

In the construction industry, Tier 1 is a Contractor referred in ISO 19650 as the Lead appointed party, who provide goods or services directly to the ultimate client. The Tier 1 are equivalent of the PAS 1192‑2:2013 lead suppliers