All case studies
Case Study

Hospital Diagnostic and Inpatient Unit

Hospital Complete
Hospital Diagnostic and Inpatient Unit

A 7,793 m² modular diagnostic and inpatient facility at Frimley Park Hospital. Project Design (IO) delivered the electrical coordination across four floors, from diagnostics and wards to the rooftop plant room.

GFA
7,793 m²
Building composition
  • Ground Floor: Diagnostic and Mammography Departments with 2 MRIs, 3 CTs, 2 Gamma Cameras, 2 Mammography units, and 2 Ultrasound Rooms.
  • First Floor: 38-bed Decant Ward with 22 single bedrooms (each with an ensuite) and 4 four-bed bays.
  • Second Floor: 36-bed Respiratory and MADU Ward with 12 Very High Dependency Single Rooms (each with an ensuite), 12 step-down single rooms (each with an ensuite), and 3 four-bed bays.
  • Third Floor: Plant room.
Services in scope

Project Design (IO) was appointed to coordinate the electrical services for this new modular hospital building - covering electrical, fire, nurse call and security systems through to construction-issue drawings.

Key tasks
  • Containment Coordination
  • Plantroom Coordination
  • Vertical Distribution
  • Coordination of 1600Amp Bus-Bar incoming supply
  • Coordination of specialist services
  • Coordination of Lighting and Small Power Services
  • Provision of construction drawings (shop drawings)
  • 723 Lighting Devices
  • 1,880 Lighting Fixtures
  • 836 Data Devices
  • 732 Security Devices
  • 662 Nurse Call Devices
  • 1,748 Fire Alarm Devices
  • 6,558 meters of Containment
Project name
Frimley Park Hospital
Project code
FPH035
Location
Frimley Park Hospital, GU16 7UJ
Client
Contact us to disclose
MEP contractor
Contact us to disclose
MEP consultant
Contact us to disclose
BS manager
Contact us to disclose
Mechanical coordinator
Contact us to disclose
Other participants
Contact us to disclose

Incoming Supply 1600Amp Busbar

Challenge

The incoming LV supply was served via a cast resin busbar system 1600 Amp, provided by the manufacturer as a 3D model. Once imported and aligned to the project coordinates, the busbar model revealed number of critical issues: for example the ground floor section was too short to reach the intended termination point, and the busbar clashed with structural elements within the second floor plantroom. These issues had not been identified by the manufacturer.

Solution

By importing and coordinating the manufacturers 3D busbar model against architecture and structure, we detected all issues. We then adjusted the route and dimensions in Revit, confirmed fixing and support locations, and issued a coordinated model and setting out information back to the manufacturer ahead of fabrication.

Incoming Supply 1600Amp Busbar

Vertical Distribution

Challenge

The consultant's design did not allocate sufficient riser space for the electrical submains and distribution boards, and the electrical and mechanical risers were not aligned. This constrained the available cable routes and began to drive changes to surrounding services and the architectural layout.

Solution

Late in the design, insufficient electrical riser space meant the original vertical distribution could not be built. By replanning the riser strategy, creating new vertical routes and repurposing existing mechanical risers, we recovered enough space for submains and distribution boards and agreed a coordinated, buildable riser layout across all disciplines.

Vertical Distribution

Plantroom Coordination

Challenge

The MEP model carried generic mechanical plant at the end of RIBA Stage 3. When the actual plant selections were confirmed, the plantroom layout had to be substantially redesigned, driving extensive recoordination and adding approximately 12 weeks to the programme.

Solution

We re-engineered the electrical scope to suit the revised plantroom layout, re-routing the cast iron busbars, cable ladder and electrical risers through the updated mechanical plant arrangement. By sequencing our design changes to track the rolling mechanical redesign, we maintained alignment between electrical and mechanical coordination throughout the extended Stage 3 to 4 transition, avoiding an additional round of late rework once the plant layout stabilised.

Plantroom Coordination

Electrical systems coordination

Coordinated lighting, power, fire alarm, nurse call and security across the building into a single federated model.

Diagnostic equipment

Coordinated the electrical provision for MRI, CT, Gamma Camera and mammography suites, including their specific power and containment requirements.

Efficiency

Improved maintenance access through coordinated containment and plant routing.

Space management

Resolved the riser and distribution-board space allocation early, protecting both the programme and the architectural layout.

The project was modelled and coordinated entirely in Autodesk Construction Cloud, with bespoke Revit families built for the specialist clinical equipment and fittings. Coordination ran in two main phases: an initial WIP and P01 issue, followed by a substantial revision once the mechanical plant was confirmed. That redesign increased the containment coordination effort by more than 50%, concentrated in the containment routes, vertical risers and small power — reflecting how much downstream electrical work depends on the mechanical plant being fixed early. Throughout, the model was kept clash-free through routine checks, allowing issues like the busbar and buffer-vessel clashes to be resolved before they affected adjacent services or the programme.

In Operation

Related project 23314_Frimley Park Hospital

Certain project details are confidential and shown as "Contact us to disclose". Figures and outcomes are presented with project context only.