This free generator load calculator sizes life safety and standby generator sets to BS 8519, BS 7671 Chapter 56, BS 9999 and the LPC Rules TB210.
PD Generator
version 3.24.0Size a three phase life safety or standby generator from the loads it must support, and read the required size and the verdict of each sizing check in the tool.
How this works
- Add your loads. Pick from the typical list (real-project values, ready to edit) or type your own. Where a field is left blank, a conservative rule of thumb is used. By the tool's own rule, a figure entered from manufacturer data is used in place of the tool's rules of thumb on every line that uses that figure. The note under the line says when a starting current or a locked rotor current (LRA) entered is not used. BS 8519:2020 20.1 recommends that the pump or motor manufacturer provides the motor parameters.
- The three phase load profile is built from those loads. The kVA and kW at each time step are calculated from each load's starting characteristic, including the worst case (TB210 / BS 8519:2020): each different sprinkler pump in turn with a locked rotor while the others start, and each order in which the different wet riser pumps can start. Where there are more cases than can be calculated for the load profile, each different wet riser pump is the duty pump once and the others start in line order, and the checks include a "Not checked" line. The generator is sized for the case with the largest sizing duty.
- Read the result. PD states the required generator size and the verdict of each sizing check in the tool. Engineering Toolkit subscribers can also print the report, which includes the load profile, the BS 7671 Reg 560.7.11 equipment record, the acceptance criteria (BS ISO 8528-5:2025 class G2), the fuel storage and the supply schematic.
Free to run for everyone. Engineering Toolkit subscribers get the fuel and endurance check, the schematic, editable Excel / Word / CSV / Text exports and My Projects.
Options: scenario, check a generator size, the supplier's data for that size, fuel philosophy, changeover time, rated power factor, fire strategy durations
Site conditions (optional): ground height, mounting of the generator, design ambient temperature, installation and enclosure
Scenario record: the basis of the worst case
Connected equipment record: BS 7671 Reg 560.7.11
Acceptance criteria for the generator selection
Fuel storage & endurance: BS 8519:2020 Table 2
Secondary supply schematic
Design notes
- 5,408scenarios (2,704 in each tier) compared one by one with 3.12.0: the recommended size changes in none of them; the steady demand rises in 2,684 and falls in none. The size changes in the 3.13.0 entry are from the mixed-load and late-start cases, counted separately.
- 40compliance checks, every claim traced to its clause
- 17typical life safety loads with real project values
- BG 70/2021Example 2 (section 9.1.3, Figure 46, page 59): locked rotor demand of the duty sprinkler pump, 1051.7 kVA in the tool compared with about 1050 kVA read off the figure
- Last reviewed
- October 2026
- Data basis
Show the full record
Starting characteristics and pump data: BSRIA BG 70/2021, including the Tables 6 to 8 pump examples (with the 1 s delta phase of BG 70/2017 Tables 8 to 10), the locked-rotor window held for 75% of the hot burn-out time unless the protective device clearance time is entered, and the Table 5 typical hot burn-out times of 6 to 38 s for IE1 and IE3 motors. The 9 to 13 s burn-out band is the tool's own, not a BG 70 figure: a default of 13 s where the hot burn-out time is left blank, and a lower limit of 9 s (a lower entry is flagged). Start sequence: sprinkler pumps immediately power is available, the duty wet riser pump 15 s after power is available, the assist 30 s after power is available, and each further wet riser pump 15 s after the one before (BG 70/2021 section 9.1.1, page 54; Technical Bulletin 210 (TB210), September 2022, TB210.8.2.1(a)6 and (a)7, the wet riser delays subject to the agreement of the authorities). Starting power factor (pf) by load type as rules of thumb: direct on line 0.30; star-delta rising from 0.30 to 0.80 across the star phase, then 0.80 through the changeover; soft start 0.45; variable speed drive (VSD) 0.90; Non-motor 0.95. A pump held in the locked-rotor window of the "Worst case" scenario is taken at 0.30 whatever its load type, as if started direct on line or through a bypass. Locked rotor current where none is entered: the BS EN IEC 60034-12:2024 maximum for the motor rating entered, at rated voltage (Table 3 where the design letter is not known), or, where chosen, the typical value of BSRIA BG 70/2021 Table 5 (page 49) for the rating and IE class (IE1 and IE3 motors, 5.5 to 280 kW). A locked rotor current entered is always used first. Defaults where a figure is left blank: locked rotor at 6 times full load current where no motor rating is entered or the rating is outside the IEC tables, a 3 s run-up at locked rotor, a 0.4 s delta re-inrush, soft start limited to 2.5 times and a VSD to 1.5 times full load current. Inputs with stated defaults: changeover time 15 s (BS 9999 37.2.3.3 b, BS 8519 6.3), rated power factor 0.8, structure fire resistance period 120 min, smoke control duration 60 min. Acceptance limits: BS ISO 8528-5:2025 Table 4 performance class G2, with the 70% variable average of a standby rating (ISO 8528-1, BS 8519 6.3); the 80% steady headroom is a PD indicative warning, not a standard limit. Fuel storage: BS 8519:2020 Table 2 with the local service tank of 6.3. 17 typical life safety loads include real project values and start times as a starting point. BS 8519:2020 20.1 recommends that the pump or motor manufacturer provides the motor parameters. By the tool's own rule, a figure entered from manufacturer data is used in place of the tool's rules of thumb on every line that uses that figure. That rule is not a requirement of BS 8519. The generator manufacturer's own sizing run is the selection of record; this is PD's position, not a requirement of a standard.
- Validated against
- Running and starting loads and fuel storage are independently verified against calculations derived from load currents, BS 8519:2020 and BG 70. Version 3.24.0 was last validated on 19/11/2026, passing 398 automated checks, including 293 fault-injection tests.
- Sizes LV life safety and standby generator sets at 400 V 3-phase from the loads entered. The worst case (locked-rotor pump plus assist start, TB210) is the default. The recommendation is a starting point. By the tool's own rule, a figure entered from manufacturer data is used in place of the tool's rules of thumb on every line that uses that figure. BS 8519 20.1 recommends that the pump or motor manufacturer provides the motor parameters. The generator manufacturer's sizing run against the class G2 limits is the selection of record. Not for HV sets or paralleled installations above 2500 kVA.
What's changedNovember 2026 · v3.24.0Engineering Toolkit subscribers get a two-part report, Part A for approval and Part B for the generator manufacturer, with a title block, 17 manufacturer fields, a load step table and acceptance criteria to BS ISO 8528-12:2022 Table 3, classification 3, beside class G2. A load profile drawing replaces the chart.
- November 2026 · v3.24.0Engineering Toolkit subscribers get a two-part report, Part A for approval and Part B for the generator manufacturer, with a title block, 17 manufacturer fields, a load step table and acceptance criteria to BS ISO 8528-12:2022 Table 3, classification 3, beside class G2. A load profile drawing replaces the chart.
- November 2026 · v3.23.0Projects whose wet riser pumps differ can reopen with a larger size or failed first load step check, as PD checks every start order. Without the lift maker's minimum voltage, the lift dip limit is 15%, not 20%. With only the motor rating entered, PD checks regeneration on PD assumptions.
- November 2026 · v3.22.0PD checks a lift's starting voltage dip and regeneration, THDv from UPS rectifiers and the rating at site conditions. Where the dip exceeds its limit, a size entered that passed in 3.21.0 reads "is not confirmed. Review needed". The rating explainer can read "above" where 3.21.0 read "within", matching the average power check.
- November 2026 · v3.21.0The wording in the tool, the printed report and the exports now states each first load step limit with its calculation and the lowest value PD has read in the engine makers' published data, and how to replace it with the manufacturer's published value. Subscriber reports and the exports list the 12 first load step values and the makers' values for a further load step. The result line also names any other failing check, and states when no listed generator accepts the step. No value, size or verdict changes, so a report saved in 3.20.0 opens with the same result.
- November 2026 · v3.20.0Each load step is checked against its applicable limit, excluding loads held for less than 1 s. The first step limit is the supplier's value where entered, otherwise 45% of rated kW, or 50% for standby up to and including 400 kVA. With load on the engine, the limit is 70% or 55% of the first step limit. These percentages are PD assumptions. A short peak above the limit is a warning only. In the sequential start advisor, moved loads start 5 s apart, not 2 s. Reports saved before 3.20.0 can open with a larger size or a fail.
- November 2026 · v3.19.0Every BS 8519 citation in the tool, the exports and the printed report now reads BS 8519:2020. Where a locked rotor current (LRA) is entered for a motor marked "N or H" above 160 kW, the note saying the BS EN IEC 60034-12:2024 Table 3 maximum is not used now states the tool's rule for using Table 3, in the tool, the printed report and the exports. The note saying an estimate from the rating is not used, the note under a sprinkler or wet riser pump line and the check on the motor rating and the full load current (FLC) now cite BS EN IEC 60034-12:2024 or BSRIA BG 70/2021 in full. The calculations, sizes and check results are unchanged.
- November 2026 · v3.18.0In "Worst case" a sprinkler or wet riser pump held in locked rotor is now taken to draw its full load current (FLC) where the locked rotor current (LRA) used is below it. With no LRA entered, the BS EN IEC 60034-12:2024 estimate of the LRA for a motor marked "N or H" above 160 kW is now the higher Table 3 maximum, not the Table 2 maximum. The peak and the recommended size can change only on these lines, and on a pump held in locked rotor they can only rise. A line saved with an old BG 70 preset name now opens with its BG 70/2021 name, unless the name was changed. The exports and the printed report now state what the LRA marks mean. A motor rating is now shown to three decimal places at most.
- November 2026 · v3.17.0BG 70 citations now name BG 70/2021, except the presets' 1 s delta phase (BG 70/2017). Motor lines have "Motor rating (kW)" and "Motor design (IEC 60034-12)". With a rating and no locked rotor current (LRA) entered, the LRA is the BS EN IEC 60034-12:2024 maximum for 0.12 to 1600 kW, otherwise 6 x full load current (FLC). Where chosen under "LRA estimate", the BG 70/2021 Table 5 typical value is used only for listed ratings (5.5 to 280 kW) of IE1 or IE3 motors. The notes, checks, exports and printed report state the LRA used and its source. Where the estimate is below 3.5 x FLC, a check line and a note state that the rating and FLC do not agree. Sizes can change only on a motor line with a rating and no LRA. The printed report's last item, status line and footer now stay on one page.
- November 2026 · v3.16.0Sprinkler and wet riser pump lines have a "Pump role"; a Standby line can name its Duty line, with no figure copied. The notes, checks, exports and printed report name each line with its role and state why where the pump held is not marked Duty. The duty and standby presets have roles. "Start again" sets the rating basis back to "Standby (ESP)". For a size entered to check, the result line names the case of any figure not from the case in the chart. The Definitions include the locked-rotor window, the deferral period and "Pump role". The check line for a long hot burn-out time states that deferrable starts are placed later only where a sprinkler pump has no clearance time entered. Projects saved before 3.16.0 open with every role Not stated. For the same entries, sizes and check results are unchanged; every pump stays in the worst case.
- November 2026 · v3.15.0In "Worst case" each different sprinkler pump is now held in locked rotor in turn with each wet riser order. Above the tool's limit of cases for the load profile, each different wet riser pump is the duty pump once, the others in line order, and a "Not checked" line says so. The tiles, chart and load steps now show the case that sets the size: a peak can fall while the size rises. A size entered to check that read "is not confirmed" can now read PASSES or "acceptable only if the manufacturer sizing run demonstrates it", never UNDERSIZED. The sequential start advisor in the checks, exports and printed report now says "the deferral period" where it said "the locked-rotor window", for the period after which it starts the deferrable loads, and states the latest end of that period over every sprinkler pump, whichever pump is held.
- October 2026 · v3.14.2An empty "Starting current" or locked rotor current (LRA) field that the line does not use now shows "n/a" (not applicable). The note under the line now lists only the start figures used. The note and "Sizing basis" in the printed report and the exports now state why an entered figure is not used. In the equipment record, an unused figure is now marked "not used". Such a figure was not used in 3.14.1 either. The calculations, sizes and check results are unchanged.
- October 2026 · v3.14.1On a direct-on-line (DOL) line, the larger of the locked rotor current and the "Starting current" entered is now used for the start and the locked rotor case. "Peak demand", "Peak engine duty" and the recommended size can rise. They can also fall with two or more different sprinkler lines, one of them DOL with a "Starting current" entered, because the line held in locked rotor can change. A checked generator that passed can now fail. The "Steady state" tiles, the endurance check and the class G2 limits did not change.
- October 2026 · v3.14.0The tool is now named PD Generator. Picking a typical load on a line whose "Ramp (s)", "Starting pf" or "Running pf" was edited now gives the same result as a new line: the recommended size can fall or rise, and a duty and standby pair of the same pump is checked. No other calculation, rating, limit or size changed.
- October 2026 · v3.13.0The steady demand is now every line running, standby pumps included; 5.0 s demands count as sustained: some sizes are one larger. Starts running past 90 s now count: sizes can rise or fall. Sprinkler or wet riser pairs whose entries differ are listed as not checked, with no size change. With pumps, no "Manual start times" check reads PASSES.
- October 2026 · v3.12.0The star-delta starting power factor now rises from 0.30 to 0.80. In "Worst case" a locked-rotor pump is taken at 0.30 whatever its load type, with a note on "VSD" and "Non-motor" fire pumps. "Starting pf" takes precedence. The kVA demand is unchanged; some sizes are smaller, a few larger. Reports saved before 3.9.1 keep their wording when reopened.
- September 2026 · v3.11.0Every label on the printed secondary supply schematic now measures 8.2 pt or more in the cases checked, against 4.0 to 5.1 pt in 3.10.0. The design notes, which are for the designer, not the client, are no longer in the report emailed to free users or the PDF export of a report saved with 3.11.0 or later. The calculations are unchanged.
- September 2026 · v3.10.0The printed report is no longer shrunk to fit one A4 sheet per page: every line of text outside the drawings now measures 8.2 pt or more; before, most text measured 3.3 to 6.2 pt. The printed report, the exports and the emailed report now read "Required generator: more than the largest standard set listed" when the sizing duty is above that set. The calculations are unchanged.
- September 2026 · v3.9.1The "Above the single-set range" check line and the design note on paralleling now cite BS 7671 560.6.9, not 560.6.8. Lines citing BS 8519:2020 6.3, 20.2 and 20.4 and BS 9999:2017 G.2.2, clauses written with "should", now read "recommends" or "should". For a size entered for checking, the printed generator size box is now green, amber or red by the result. The calculations are unchanged.
- September 2026 · v3.9.0The tool now looks like the PD Power Distribution tool, and the "Start again" button is now in a dark bar at the top. The "Required generator" line and the printed generator size are now blue, not copper. On a phone, the "Pick a typical load to add" list now stays inside its panel. The calculations are unchanged.
- September 2026 · v3.8.8The wording in the tool was revised in plain UK English: the compliance record line now says in the tool. The ratings, the checks, the printed report and the exports are unchanged
- September 2026 · v3.8.7The notes written inside the program code were rewritten in plain UK English. The calculations, the wording shown in the tool, the printed report and the exports are unchanged
- September 2026 · v3.8.6The wording in the tool and in the report was revised in plain UK English. The fuse requirement now reads that the fuse shall not clear the stalled rotor current before 75% of the period needed for the windings to fail (BS 8519 20.1, TB210 8.2.1(e)). No rating, check or limit changed.
- September 2026 · v3.8.5A load line moved onto the Fire DB / small power category now takes the Non-motor load type at that moment, not only when the line is created on that category; the check line for a Fire DB line left on a motor load type stays.
- September 2026 · v3.8.4The rating basis choice (standby or prime) is now shown only when a size is entered for checking; with no size, the recommendation is always the standby rating. A new custom Fire DB or small power line now takes the Non-motor load type. No factor, duration or limit changed.
- September 2026 · v3.8.3The equipment record now shows the full load current as entered, to one decimal place, rather than rounded to a whole ampere. The hot burn-out time field now appears on pump lines only, where it is used for the stalled rotor window. No rating, default or check value changed.
- September 2026 · v3.8.2Every numeric input now names the figure that could be entered by mistake: for example, the stalled current is the delta (direct-on-line) locked-rotor value, not the star value. A stalled current below 3.5 x FLC on a pump or motor line is flagged in the tool for checking. No rating, default or check value changed.
- September 2026 · v3.8.1The light-running note on the steady duty check and the equipment record no longer cites BS 8519 6.3 for the on-load test regime, which that clause does not set; the note now points to the set manufacturer's operating requirements. No rating, default or check changed
- September 2026 · v3.8.0Changeover time (15 s, BS 9999 37.2.3.3 b)), set rated power factor (0.8), structure fire resistance period (120 min) and smoke control duration (60 min, never lower) are now inputs with these defaults, and each pump line has an optional protective device clearance time. The 80% steady headroom check now gives a labelled PD warning, with UNDERSIZED reserved for demand above the nameplate.
- September 2026 · v3.7.2The sizing principle line states BS 8519:2020 6.3 as the recommendation it is, a set sized to maintain the maximum design load and support the worst-case transient and fault conditions, rather than as a requirement. No rating, default or check changed
- September 2026 · v3.7.1The wording was revised in plain UK English: the sizing duty and the sizing case are named as such, manufacturer data takes precedence, a limit is called a limit, plurals written out, the on-screen text has no dashes. No rating or check changed
- August 2026 · v3.7.0Free use is now measured in sessions: three days of anonymous use, then your email continues free use with no password and no account. The compliant worst-case engine stays free and unchanged; the report goes by email for free users, with print as part of the Engineering Toolkit
- August 2026 · v3.6.3Subscriber-facing copy states what the Engineering Toolkit adds rather than what the free preview lacks, and the report footer now lists what the Toolkit adds: the worst-case engine and the staggering advisor are free to everyone
- July 2026 · v3.6.2The tool copy states plainly that it sizes three phase sets
- July 2026 · v3.6.1Two precision fixes from a full claims validation: the G2 frequency limit now cites the ISO 8528-5 Table 4 transient difference row with the droop value, and a staggered run states its actual offsets instead of a fixed 15 s
- July 2026 · v3.6.0A stalled rotor window that outlasts the G2 recovery limits (BS ISO 8528-5 Table 4) is no longer treated as a momentary transient, so the recommendation is now the greater of the steady load, the sustained kVA and kW, and half the momentary peak. Check mode now states PASSES, conditional or UNDERSIZED explicitly.
- July 2026 · v3.5.1Desktop fix: the equipment rows no longer scroll sideways because of hidden guidance popouts
- July 2026 · v3.5.0Paid report gains guidance on the rating (ISO 8528-12): why conformity is mandatory for a safety source (BS 7671 560.6.13), prime against standby in practice, and the 70% variable average rule applied to your own calculation
- July 2026 · v3.4.1The stall window returns to the published guidance basis, locked rotor held for 75% of the hot burn-out time, with the 75% to 100% clearance band disclosed on the report
- July 2026 · v3.4.0The worst-case engine is free for every user: the free tier had been falling back to manual and reporting an undersized generator, 60 kVA against 100 kVA on the same input. The stalled rotor window takes the full hot burn-out time, and the report header reads REQUIRED GENERATOR with the caveats in the design notes
- July 2026 · v3.3.1Audit pass: the fallback values for time step, run-up and delta transition brought back in line with the audited configuration (0.1 s, 3 s, 0.4 s)
- July 2026 · v3.3.0The stalled rotor window was corrected against BG 70/2017: the fuse must not clear before 75% of the hot burn-out time, so staggered starts now clear the full burn-out time plus one second. New advisories above a 15 s burn-out time, and on a VSD-fed pump with an entered locked rotor current
- July 2026 · v3.2.0Staggering advisor: the tool moves every deferrable load beyond the fuse clearance window at 2 s intervals, never the sprinkler or wet riser pumps, and quantifies the saving with a one-click apply. Check each system response requirement against the fire strategy first
- July 2026 · v3.1.0The hot burn-out time default was raised from 9 to 13 s, the worst case of the field guidance band. Entries below 9 s now raise a warning, and supplier data takes precedence over the default.
- July 2026 · v3.0.2A line named like a pump, lift or smoke fan but categorised as something else now raises a warning naming the line and the category expected
- July 2026 · v3.0.1Chart peak label no longer collides with the milestone labels
- July 2026 · v3.0.0Customer-first layout: one sentence and the standards badges first, the typical loads picker as the main panel, scenario and fuel choices in a quiet options strip, and column headers in plain English. Engine, report and exports untouched
- July 2026 · v2.6.1Sprinkler or wet riser pumps in the manual scenario now warn that the stalled rotor case is not applied and the figures may understate the requirement
- July 2026 · v2.6.0The starting profiles were audited against field practice: locked rotor held through the run-up for DOL, a star ramp then a delta re-inrush for star-delta, linear ramps for soft start and VSD. The time step was refined from 0.5 to 0.1 s so the re-inrush cannot fall between samples
- July 2026 · v2.5.2Two attributions were corrected: VSD fail-safe fire mode to BG 70/2017, and the evacuation lift duration basis to BS 9999 G.2.2 with 120 minutes adopted
- July 2026 · v2.5.1Chart milestone labels at or before supply availability sit left of their line, clear of the curve
- July 2026 · v2.5.0The sprinkler presets were restructured as duty and standby pairs: the duty pump draws the locked rotor current and is the unit modelled in stalled rotor, while the standby starts at full starting current (TB210 8.2.1).
- July 2026 · v2.4.5Operating philosophy hint cut to half its length
- July 2026 · v2.4.4Row picker dropdown no longer shows a blank list
- July 2026 · v2.4.3The guidance popout was restyled as a wide white strip that fits the length of its text.
- July 2026 · v2.4.2The hover guidance was restyled as a white card.
- July 2026 · v2.4.1Hover guidance no longer doubles up, and the row picker draws its own chevron
- July 2026 · v2.4.0The sprinkler activation input was removed: demand is present the moment the supply is available, since a delay could only make the result less conservative. The chart window grows to the last real start event
- July 2026 · v2.3.0The timebase was corrected to the BS 9999 basis: t = 0 is the mains failure, the start-up sequence occupies the first 15 s, and every load start time is an offset from the supply becoming available
- July 2026 · v2.2.2Per-row load picker fills a line from the typical loads library, everything editable after picking
- July 2026 · v2.2.1The typical loads library was extended to a full real project schedule of 15 loads, and the whole building can be preloaded with one click.
- July 2026 · v2.2.0The required generator now leads the report and the results card, the wording is plain English throughout, and a typical loads preset library was added
- July 2026 · v2.1.0The voltage input was removed (fixed 400 V, the UK nominal); load rows are now one line with an advanced expander, every field has hover guidance, and power factors are resolved automatically by load type
- July 2026 · v2.0.0Complete rebuild on the Engineering Toolkit model: a time-step engine to BS 8519:2020, BS 7671 Chapter 56, BS 9999:2017 and LPC TB210, with per-equipment starting characteristics, the worst-case scenario, G2 acceptance criteria, fuel storage to BS 8519 Table 2 and the Reg 560.7.11 equipment record
