On this page:

    UK Earthing & Bonding Design Reference

    (Edition 2025 – aligned with BS 7671:2018+A2:2022, Amendment 3 (2024), and draft Amendment 4 (2026), also drawing from official UK Power Networks standards)

    Scope, Authority & Legal Framework

    • Applies to earthing, main protective bonding, supplementary bonding, and high-integrity protective conductors (HIPCs) for low voltage (<1 kV a.c.) electrical installations.

    • Mandatory requirements are directly referenced from BS 7671, with clause numbers provided.

    • Informative and best-practice guidance is referenced from:

      • IET Guidance Note 8 (Earthing & Bonding)

      • On-Site Guide (OSG)

      • Energy Networks Association (ENA) G12/3

      • Relevant DNO (Distribution Network Operator) policies (e.g., SPEN EART-01-002 for PNB)

    • Statutory requirements include:

      • Electricity at Work Regulations 1989

      • Electricity Safety, Quality & Continuity Regulations 2002 (ESQCR)

    A distributor shall, when providing a new connection at low voltage, make available his supply neutral conductor or, if appropriate, the protective conductor of his network for connection to the protective conductor of the consumer’s installation” – ESQCR Regulation 24(4)

    Identifying the Supply Earthing Arrangement

    Refer to the system identification flowcharts and records. Typical arrangements:

    Visual/Record IndicatorLikely SystemTypical ZeNotes
    CNE cable & multiple distributor electrodesTN-C-S (PME)≤ 0.35 ΩReg 411.4.1 + ENA G12/3, EDS 06-0016, Table B.4
    CNE cable & single electrode at intakeTN-C-S variant (PNB)≤ 0.35 ΩTreated as TN-S inside; confirm with DNO. EDS 06-0016, Section 6.5
    Separate neutral & earth throughout supplyTN-S0.35–0.8 ΩNo PEN in building, EDS 06-0012, Table 4-2
    Customer electrode only, no distributor earthTT≤ 21 Ω (with RCD)BS 7671 Reg 411.5
    PEN not separated inside premisesTN-Cn/aNot permitted indoors (BS 7671 Reg 312.2)

    Amendment 3:2024 recommends an additional earth electrode for all TN systems (Reg 411.4.2).

    Earthing network diagrams from UKPN Library

    Protective Neutral Bonding (PNB)

    Although PME is the preferred option protective neutral bonding (PNB) may provide a better solution in circumstances where it is not practical to install the LV earth at the transformer. In a PNB earthing system the LV neutral conductor is connected to an earth electrode at a point remote from the transformer at or near the customer’s supply terminals […].

    PNB may only be used if the following criteria are satisfied:

    • A maximum of four customers.
    • The connection to earth shall be made as close as possible to customer’s supply terminals and no more than 40m from the furthest customer.
    • The earth electrode shall have a maximum resistance of 20Ω.
    • The earth electrode shall be a minimum of 8m from any HV earth or HV metallic sheath cable.
    • The metallic sheaths of any LV cables shall also be connected to the earth electrode.
    • The transformer tank and associated HV metalwork shall be connected to the HV earth electrode.
    • A PNB earth terminal shall be treated as a PME earth terminal and the appropriate labelling applied (Refer to EDS 06-0017).

    Protective Earthing

    The purpose of protective earthing is to ensure that, in the event of a fault, such as between a line conductor and an exposed-conductive-part or circuit protective conductor, sufficient current flows to operate the protective device, i.e. fuse to blow, circuit-breaker to operate or RCD to operate, in the required time.

    Every exposed-conductive-part (a conductive part of equipment that can be touched and which is not a live part but which may become live under fault conditions) shall
    be connected by a protective conductor to the main earthing terminal and, hence, the means of earthing for the installation. [411.4.2, 411.5.1 BS7675]

    Main Protective Bonding

    When Required

    Bond every incoming extraneous-conductive-part (e.g., water, gas, oil, structural steel, lightning down-conductors, metallic cable sheaths) to the Main Earthing Terminal (MET) “as near as practicable to the point of entry” (Reg 544.1.2).

    Conductor Sizing

    For PME / PNB (per Table 54.8, BS 7671):

    PEN (Cu-equiv.)≤35 mm²>35–50 mm²>50–95 mm²>95–150 mm²>150 mm²
    MPB (Cu)10 mm²16 mm²25 mm²35 mm²50 mm²

    For Non-PME (TN-S or TT):

    Minimum: ½ earthing conductor CSA, at least 6 mm², maximum 25 mm² Cu (BS 7671 Reg 544.1.1).

    Earthing Conductors & Electrodes

    Buried earthing conductor:

    • 16 mm² Cu (protected)

    • 25 mm² Cu (unprotected)
      (Table 54.1)

    Earth electrodes:

    • Resistance as low as practicable.

    • For TT: select electrode(s) to ensure Ra×IΔn≤50 V (BS 7671 Reg 411.5.3).

    Extraneous-Conductive-Part Assessment

    “…a conductive part liable to introduce a potential, generally Earth potential, and not forming part of the electrical installation.”

    Three-Step Method

    Step 1: Definition Application
    Apply the complete BS 7671 definition – all three criteria must be met.

    Step 2: Resistance Test (IET GN 8 Method)

    • Measure resistance between part and MET

    • R > 22 kΩ: May be treated as not extraneous

    • R ≤ 22 kΩ: Apply engineering judgement

    Step 3: Documentation
    BS 7671 Regulation 642.3: All decisions and test values must be recorded

    Supplementary Equipotential Bonding

    Resistance Criterion (BS 7671 Reg 415.2.2)

    R≤50 V/Ia between simultaneously accessible conductive parts.

    RCD IΔn 30 mA100 mA300 mA
    Max R1.67 kΩ500 Ω167 Ω

    Conductor Sizing

    Follow Regs 544.2.1–544.2.2 or OSG Table 4.6 (e.g., 2.5 mm² Cu with mechanical protection, 4 mm² otherwise).

    High-Integrity Protective Conductors (BS 7671Reg 543.7)

    • Required where protective-conductor current >10 mA (e.g., harmonic filters, UPS, VSDs).

    • Ring final circuits with ring CPC inherently satisfy.

    • Acceptable alternatives:

      • Dual single-core CPCs

      • Multicore cable with split armour

      • Separate conduit

    • Label distribution boards:
      “High-Integrity Protective Conductors – do not remove CPCs” (BS 7671 Reg 543.7.1.205).

    Protective Devices & RCD Types

    DeviceAcceptable UseClause
    Type ACFixed loads proven free of d.c. residualsBS 7671 Reg 531.3.3
    Type AGeneral socket / lightingDefault
    Type FHeat pumps, induction hobs, EV chargingManufacturer spec
    Type BPV inverters, VSDs, battery systemsManufacturer spec, IEC 62423 requirements

    Amendment 3:2024 introduces new bidirectional RCBO/RCD symbols for devices supporting power flow from embedded generation.

    Worked Example - Adiabatic CPC Sizing

    Circuit Parameters:

    • 230 V TN-S radial circuit

    • 32 A Type B MCB

    • Zs = 0.15 Ω

    Calculation Steps:

    Step 1: Fault Current
    Ief = Uo / Zs = 230 / 0.15 = 1,533 A

    Step 2: Operating Time
    t = 10 s (from manufacturer’s time/current curve)

    Step 3: Energy Calculation
    I²t = (1,533)² × 10 = 23,508,900 A²s

    Step 4: Conductor Sizing
    S = sqrt(I²t) / k
    Where k = 143 (for 70°C PVC copper – BS 7671 Table 54.4)
    S = sqrt(23,508,900) / 143 = 33.9 mm²

    Step 5: Selection
    Select next standard size: 35 mm² Cu

    Construction & Demolition Sites (Section 704)

    "A PME earth terminal shall not be provided to construction or demolition sites because it is not possible to verify that the installation continuously complies with the bonding requirements of BS 7671"

    • Preferred earthing: TT or PNB.

    • PME is allowed only if all ECPs are reliably bonded (Reg 704.411.3.1).

    • RCDs:

      • 500 mA time-delay for circuits >32 A

      • 30 mA for circuits ≤32 A (Reg 704.411.3.2)

    • ENA G12/3 warns of neutral-current diversion risk on steel-framed PME sites—electrode system often mandated.

    Permitted Earthing Systems:

    1. TT with RCD protection (preferred)

    2. TN-S from dedicated transformer

    3. TN-S via isolating transformer

    Electrode Separation Requirements:

    • Minimum 2m from PME electrodes

    • Minimum 8m from HOT substations

    Common Errors & How to Avoid Them

    ErrorWhy It MattersCorrect Approach
    Confusing PNB with PME; undersizing MPBPEN size may differTreat as TN-S unless DNO confirms PME; size bonding to Table 54.7 if non-PME
    Taking 22 kΩ as a mandatory pass/failIt is informative onlyAlways use BS 7671 definition; 22 kΩ is a screen
    Undersizing bonding to outbuildingsSeparate structures need own MPBBond to MET in that building, CSA ≥ CPC of supply SWA
    Omitting extra electrode on TN-C-SNow recommended (Amd 3)Fit 2–4 m rod or plate; record Ra value
    Leaving PEN combined inside a buildingTN-C prohibited indoorsSeparate PEN at intake (TN-C-S) or use TT

    Functional Earthing in Amendment 4 (2026): Section 545 Guide

    Amendment 4 to BS 7671 introduces a new Section 545 specifically addressing functional earthing and functional-equipotential-bonding for Information and Communication Technology (ICT) equipment and systems [1] [2] [3]. This section represents a significant development as technology continues to evolve, particularly in renewable energy systems, data centers, and communication networks.

    Key Requirements

    Dedicated Functional Earthing Terminals

    • Main Functional Earthing Terminal (MFET): When multiple functional bonding conductors are present, a separate MFET must be installed for ease of connection [4]

    • Single Connection Rule: The MFET must be connected to the Main Earthing Terminal (MET) only once[4]

    • Combined Terminals: The MFET and MET may be combined where appropriate [4]

    Resistance Requirements

    • ≤2 Ω to earth: This is the expected maximum resistance requirement for functional earthing systems [5] [6]

    • This low resistance value ensures effective operation of ICT equipment and proper electromagnetic compatibility (EMC) performance

    Segregation from Protective Earths

    • Insulation Requirement: Functional bonding conductors must be insulated when not locally connected to the protective-equipotential-bonding system [4]

    • Separate Installation: Functional bonding conductors must be installed separately from protective conductors [4]

    • Prevention of Interference: This segregation prevents protective conductor currents from flowing along functional earthing conductors [7]

    Conductor Requirements

    Identification

    • Pink Color Coding: Functional earth conductors must be identified using pink sleeving as per BS 7671:2018+A2 [8] [9] [10]

    • Alphanumeric Designation: Use “FE” for functional earth conductors [11]

    • Clear Marking: All functional earthing connections must be clearly labelled to distinguish from protective earthing [12]

    Minimum Cross-Sectional Areas

    Based on the draft requirements [4]:

    • 2.5 mm² Cu (if mechanical protection is provided)

    • 4 mm² Cu (if mechanical protection is not provided)

    • 16 mm² Al (alternative material specification)

    Applications and Systems Covered

    Section 545 applies to ICT systems including [3] [13]:

    • Broadcast equipment

    • Communication technology systems

    • Computer network systems

    • Data centers and telecommunications installations

    • Solar PV and battery storage systems

    • Power over Ethernet (PoE) applications

    Design Considerations

    EMC Requirements

    • Electromagnetic Compatibility: Functional earthing is essential for maintaining signal integrity and reducing electromagnetic interference [14] [15]

    • High-Frequency Performance: Unlike protective earthing, functional earthing must handle high-frequency disturbances effectively [15]

    • Signal Reference: Provides a stable reference potential for sensitive electronic equipment [13]

    Installation Arrangements

    • Mesh Bonding Networks: ICT systems should use mesh-type bonding networks (MESH-BN) for optimal performance [13]

    • Multiple Interconnections: The functional earthing system should augment the main earthing system through multiple interconnections [13]

    • Proximity Requirements: Functional earthing should be located as close as possible to protected equipment [15]

    Compliance Timeline

    • Publication Date: Amendment 4 is expected to be published in 2026 [1] [2]

    • Implementation: All new installations will need to comply with Section 545 requirements once Amendment 4 becomes effective

    • Current Status: The requirements are currently in draft form and subject to revision based on public consultation feedback

    On This page

      Leave a Reply

      Your email address will not be published. Required fields are marked *

      share this page