On this page:

    Life Safety Generator selection guide

    If the secondary power supply is provided for firefighter’s lift, it must be capable of operating the firefighter’s lift at its full rated load and speed for a minimum duration of 120 minutes. [BS 8519:2020] However; the minimum fuel storage is 4h if the generator activates only in fire conditions. [BS 8519:2020, Table 2 (BS EN 12101-10:2005)]

    Independent Primary & Secondary Power Supplies:
    • The secondary supply should be completely independent of the primary supply, preferably an automatically started standby generator. [BS 8519:2020]
    Fire-Resistant Enclosures:
    • Generators should be housed in a 120-minute fire-resistant enclosure [REI, EI or ESa – BS EN 13501-2:2016]
    Minimum Fuel Storage Requirements :
    • 4 hours if the generator activates only in fire conditions.

    • 8 hours if it activates whenever the primary power source fails.

    • 72 hours for applications beyond life safety and fire-fighting.

    For applications other than life safety and fire-fighting, the time period is as determined by the fire engineered strategy.

    [BS 8519:2020, Table 2]

    Key Steps in Life Safety Generator Selection

    Identify Life-Safety Loads

    Life safety generators must support critical systems that require backup power, including:

    • Fire Sprinklers & Hydrant Pumps (TB210, BS EN 12845)

    • Smoke Extract Fans (BS 9999)

    • Fire-Fighting Lifts (EN 81-72)

    • Automatic Opening Vents (AOVs) (BS 9999)

    • Corridor & Staircase Pressurization Fans (BS 9999)

    • Fire Alarm Panels & Emergency Lighting (BS 9999, BS 8519)

    Regulatory References:

    • BS EN 12845: sprinkler system electrical supply

    • BS 9999 / BS 9991: fire engineering and evacuation strategy

    • BS 8519: fire-resistant cables for life-safety systems

    Determine Starting Inrush & Locked-Rotor Current

    Each system requires power, but not all loads are calculated in the same way.

    To correctly size both the primary mains supply and secondary generator, BS 8519:2020 requires pump/motor manufacturers to provide:

    • pump rating, kW;
    • method of starting, star/delta, soft start;
    • voltage, V;
    • voltage (min), V;
    • full load current, A;
    • starting current, A;
    • duration of star phase, s;
    • starting current (delta), A;
    • duration of delta phase, s;
    • starting power factor;
    • locked rotor current star, A;
    • hot burn-out time, s; and
    • starter fuse selection.

    Requirements for Sprinkler Pumps

    Burnout Time Considerations:

    Worked example

    Duty pump stalled at LRA 199 A, standby at full starting current 66 A (TB210 8.2.1(a)6: one pump in a stalled rotor condition and any other(s) at full start current).

    Combined current = 199 + 66 = 265 A
    Apparent power = 1.732 x 400 V x 265 A = 183.6 kVA, held while the stall persists.

    How long it persists: the fuse must not clear the stalled current before 75% of the motor hot burn-out time (BS 8519 20.1; TB210 8.2.1(e)) and clears by the burn-out limit. BG 70 models clearance at approximately 75%. On a 13 second burn-out that is a 10 to 13 second window at 183.6 kVA.

    That transient does not need a 200 kVA generator: an alternator can supply kVA above its rating for seconds, provided it holds the G2 limits. It needs a set whose manufacturer run proves this step, and a start strategy that keeps every deferrable load (fans, lifts, boosters) out of the stall window. Staggering them past it is how the generator gets smaller. Run this case in the free calculator: the worst case is the default, and the staggering advisor quantifies the saving.

    Burn-out time is motor-specific: BG 70 Table 6 lists typical values from about 6 to 50 seconds by rating and efficiency class, with high-efficiency IE3 and IE4 motors surviving longest. BG 70 then makes it a design parameter: the hot burn-out time “should be limited to 15 seconds and the motor protection selected accordingly”, or the stability of the distribution suffers. Field practice for smaller pumps sits at 9 to 13 seconds; the supplier datasheet applies. Convention worth adopting: enter the LRA on the duty pump line only, the standby line’s role in the worst case is starting at full current, not stalling.

    Motor Interlocking

    The secondary supply should be sized to account for all connected loads. If the secondary supply also powers load other than the firefighter’s lift(s), a sequenced start-up may be used to help manage the total power demand. [BS EN 81-72:2020, Annex C] 

    Motor Interlocking:

    • Sequential Load Start: Where possible, design your control system to stagger the load start time. For example, it may be possible to delay the start of other loads while the sprinkler pump is in the LRA

    • Staggered Fan Start: Where possible start smoke fans after pumps reach full speed.

    • Firefighting Lift: Once the power supply is restored, the lift must be operational and ready for use within 60 seconds. [BS EN 81-72:2020, 5.10]

    • When lifts other than the designated firefighters’ lift(s) are connected to the secondary power supply – such as for returning them to the fire service access level – strategies like sequential activation and speed reduction may be implemented to regulate overall power demand. [BS EN 81-72:2020 Annex C]

    Two TB210 points that get missed. The sequenced start-up concession is for wet riser pumps, not sprinklers: the first wet riser starts in a stalled rotor condition 15 seconds later, further pumps at 15 second steps, and it is “subject to the agreement of the authorities” (TB210 8.2.1(a)7). Sprinkler pumps start the moment power is available. And the generator arrangement itself “shall be agreed by the fire insurer at the planning stage” (TB210 8.2.1(a)2), so get that agreement in writing before the design freezes.

    Generator rating: prime or standby, to ISO 8528-12

    BS 8519:2020, 6.3: “The rating of the generator should be selected in accordance with BS 7698-12, ISO 8528-12 as either prime or standby rated; for the standby set the variable average power output should not exceed 70%.”

    The standard permits either rating, however conformity with ISO 8528-12 is not optional: BS 7671:2018+A4:2026 Reg 560.6.13 states a rotary generating set used as a safety source shall conform to BS ISO 8528-12. A set quoted without it fails the wiring regulations, not just the design guide.

    • Prime (PRP): unlimited running hours on a varying load, capped average, short-period overload allowance under the ISO 8528-1 conditions. Suits sets that also serve non-emergency duty.
    • Standby (ESP): emergency-only duty. Higher rating from the same engine, but no overload capability at all and limited expected hours per year (manufacturer literature; ISO 8528-1 defines the rating conditions). The usual life safety choice, because the set runs only on mains failure.

    The 70% rule, read correctly: it limits the variable average power, the average of the fluctuating load over a 24 hour running period, not any instant of it. It protects the engine thermal life. The seconds-long starting transient is judged separately, against the alternator short-time capability and class G2 (below).

    Note: “Mission Critical Standby” and similar tiers are manufacturer commercial ratings, not ISO 8528 classifications. Specify prime or standby to ISO 8528-12 and let the manufacturer map their range onto it.

    Generator Sizing Considerations

    On a life safety set the transient sets the frame size, so a low steady-state load factor is normal, often 20 to 30%. Two limits then apply: the standby variable average must not exceed 70% (BS 8519 6.3), and sustained light running risks wet stacking, so provide an on-load periodic test regime; BS 8519:2020 sets no test interval, so take it from the set manufacturer’s operating requirements. BSRIA BG 70 puts the other bound plainly: “it is equally important that the generator set is not oversized.”

    Performance class G2: the numbers the selection must meet

    BS 8519:2020, 6.3 requires the electrical output to be “classified as G2 or better”. BS ISO 8528-5:2013 Table 4 gives the class G2 operating limits your transient study must satisfy:

    • Transient voltage deviation on sudden power increase: within -20%, recovering within 6 seconds.
    • Transient frequency deviation: within -(10 + droop)%, recovering within 5 seconds.
    • Steady-state voltage deviation: within plus or minus 2.5%.

    The evidence rule. Require the manufacturer sizing run (GenSize, SpecSizer, GenSelect or equivalent) to show your worst load step, stalled pump plus assist start, with the resulting dip and recovery against these limits, at the installed ambient and enclosure conditions. A verbal confirmation that “the software allows for it” is not design evidence. Our Generator Load Calculator prints these acceptance criteria on every report, so the requirement travels with your submission.

    Regenerative Drives in Lifts

    Modern traction lifts often use regenerative drives that feed braking energy back into the power supply. While this is efficient during normal operation, it presents a challenge when the lift is running on a standby generator. BS EN 81-72:2020 Annex C warns that if the generator cannot absorb this reverse power – typically beyond 10% (indicative; the set manufacturer declares the actual reverse-power acceptance) of its rated output it may become unstable, leading to overspeed or damage. For example, a 100 kW generator should only handle up to 10 kW of regenerative power safely; exceeding this can trip the generator or disrupt other life safety systems.

    To address this, there are two main design strategies: size the generator large enough to absorb expected regenerative energy, or provide an alternative means of dissipation. Oversizing the generator is often the most straightforward approach.

    Concurrent loads like smoke fans can help absorb regeneration, but designers should check cause & effect strategy to ensure these are being active. The safest route is to size the generator to handle regen independently.

    Alternatively, braking resistors can be fitted to the lift drive to convert excess energy into heat during generator operation.

    For larger or multi-lift systems, a permanent load bank may be installed to soak up reverse power automatically. While effective, these options add cost and complexity, so are typically used only when upsizing the generator is impractical.

    In all cases, Annex C makes clear that regenerative energy must be explicitly addressed to ensure system safety.

    Timing

    The secondary supply must be capable of providing power within 15 seconds of the failure of the primary supply (BS 9999:2017, 37.2.3.3 b); BS 8519:2020, 6.3, citing BS 9999 and BS EN 12845). In BS 7671:2018+A4:2026 terms this is an automatic supply classified “medium break” (Reg 560.4.1, medium break). The 15 seconds is consumed by the start-up sequence itself: ATS detects, generator starts and accelerates, holds stable voltage and frequency, ATS closes. Loads can only start after it.

    In the event of a mains or sub-mains power failure, the ATS should detect the loss of supply, initiate the start-up of the life safety generator, and automatically switch to the secondary power source. Once power is restored, the firefighter’s lift must be operational and ready for use within 60 seconds. [BS 8519:2020, 20.4].

    Short-Circuit Protection: Generators have lower short-circuit currents than the grid. Thermal-Magnetic (TMD) circuit breakers are recommended due to their ability to operate effectively with limited fault current.

    Motor Contributions:

    Running motors can briefly contribute to fault current by feeding energy back into the system during a fault. If the total motor load exceeds 25% of transformer capacity, its contribution must be considered. The estimated fault contribution is 3.5 times the nominal motor current (Iscm = 3.5 * In per motor a fault-study convention; confirm against the protection study). This can impact the selectivity of protective devices and must be evaluated when setting short-circuit protection.

    If the lift(s) regenerates energy:

    Generators generally have limited capacity to absorb regenerated energy. The generator should either be appropriately sized to handle this energy or alternative methods should be implemented to manage the excess power. [BS EN 81-72:2020 Annex C]

    Locked Rotor Current Takes Precedence Over Harmonics

    While non-linear loads introduce harmonics, the primary concern in generator sizing is ensuring adequate capacity for Locked Rotor Current (LRA) of motors. As the generator is already oversized to handle LRA, additional oversizing for harmonics is typically unnecessary. However, in cases of excessive harmonic distortion, Harmonic Filters, Line Reactors, or K-Factor Rated Alternators may be used for mitigation.

    Automatic Transfer Switch (ATS)

    ATS Location

    • must be located where the fire and rescue service can reach it, in the plant room or fire-fighting shaft positions set by BS 8519:2020, clause 9 (BS 9991:2024, 21.1 defers electrical design for life safety and firefighting equipment to BS 8519)
    • must be installed within a fire-protected area. [BS EN 81-72:2020 5.1.7]
    • must be accessible either directly from this vertical fire compartment or via a fire-protected route. [BS EN 81-72:2020 Annex I, I.5]
    • within plant room(s) housing the life safety, fire-fighting or other critical system equipment;
    • If The ATS is serving the firefighters’ lift, it should be located within the fire-fighting shaft outside the lift well or within a fire-protected building fabric enclosure directly adjacent to the fire-fighting shaft [BS 8519:2020, Section 9]
    • The main car park extract fan control panel should be located in the same fire-resisting building fabric enclosure as the run and standby extract fans, fed by an ATS located in the same building fabric enclosure. [BS 8519:2020, 20.3]
    • When smoke clearance system  uses impulse or jet fans, their power supply should originate from the same fire-protected building enclosure as the smoke extract fans. They may be connected through a shared ATS. [BS 8519:2020, 20.3]

    ATS Requirements

    • Any switchgear space outside the lift well and beyond a fire compartment must have a fire resistance level equivalent to that of the fire compartment(s). Similarly, any connecting elements, such as electrical cables or hydraulic pipes, that pass between fire compartments must also be adequately fire-protected. [BS EN 81-72:2020 5.7.2 ]
    • The primary and secondary power supply cables must terminate at a changeover device (ATS). [BS EN 60947-6-1]
    • If building occupancy depends on the functionality of life safety and fire-fighting equipment, a single or dual bypass system should be implemented.

      Note: If a single bypass is used, it should be on the primary power supply. [BS 8519:2020, 9]

    Typical ATS sizes based on Mertech

    • SBP – Single bypass
    • DBP – Dual bypass

     

    Frame Size (Amps)Height (SBP | DBP)Width (SBP | DBP)Depth (SBP | DBP)
    45600 | 800800210
    63600 | 800800210
    100600 | 800800210
    125600 | 800800210
    160800 | 12001200300
    250800 | 12001200300
    3501000 | 16001600300
    4001000 | 16001600300

    Automatic Transfer Switch (ATS): BS 9991:2024 compliance

    • Single component with an integral controller from the same manufacturer
    • Status monitoring for: 
      • Primary and secondary supply availability
      • Switchover position (“On Primary Supply” or “On Secondary Supply”)
    • Fault indication, which must be linked to:
      • The fire alarm system
      • The firefighting lift control switch (if applicable)

    Remote indication of Life Safety Generator status

    Remote indication of generator status is required by BS EN 12845, BS 8519, and BS 9999. The remote indication (mimic panel) should be positioned to allow rapid identification and response by the fire service on arrival, as mandated for higher-risk buildings under the Building Safety Act and Gateway 2 compliance.

    This can be achieved by the use of a configurable addressable matrix panel, such as the DS52 series, which offers a practical and compliant method for providing clear and accessible remote indication of life safety generator and ATS status at designated fire service locations, including reception or entrance lobbies.

    The panel shall be interfaced with the building’s fire alarm system, and provide key operational states, such as generator running, fault, changeover status, and battery health.

     

    ATS Panel Integration

    Each ATS need a signal cable running back to the generator. The ATS panels send a two-wire start/stop signal to the generator and manage all monitoring and switching. Typically timers for mains restoration are built-in, which matters for life safety compliance.

    Remote Indication

    • Typically remote indication panels are supplied with LED indicators showing:

      • S1 available

      • S1 on-load

      • S1 bypass

      • S2 available

      • S2 on-load

    Fuel Level Monitoring

    • Fuel percentage is displayed directly on the generator controller.

    Cabling, Commissioning, and Communication

    • Site electricians are typically responsible for all cabling.

    • Generator commissioning and sign-off are performed by the supplier.

    • Communications utilise RS485 (APM303 controller as standard).

    • Fixed volt-free contacts pack includes:

      • Genset running

      • General shutdown

      • Low fuel level

    Ancillary Supplies

    • A 13A single-phase supply is needed for the generator water jacket heater and battery charger.

    • This supply can be sourced from the nearest ATS or a local fused connection unit.

    For more detailed guidance on the Remote indication of Life Safety Generator status please go to:

    Mimic Panels for Life-Safety Generators: a UK Designer’s Guide

    Car park smoke control systems

    Car park smoke control systems are part of the Life Safety System, fed from the Generator. The main car park extract fan control panel should be located in the same fire-resisting building
    fabric enclosure as the run and standby extract fans, fed by an ATS located in the same building fabric enclosure.

    Cabling , Containment and Fixings

    Both the primary and the secondary supplies should be protected against fire and water damage and be separated from each other throughout the installation, by adopting diverse cable routes.

    Cables for life safety, fire-fighting, and other critical systems must be installed on a dedicated cable support system, separate from other cable installations. [BS 8519:2020, Section 7.3]

    If both the primary and secondary power supplies are located on the ground floor or roof level, they must be adequately protected to minimize the risk of a fire affecting both sources. This can be achieved by enclosing each supply within a 120-minute fire-resistant enclosure (REI, EI, or ESa) in accordance with BS EN 13501-2:2016, or by providing sufficient separation, supported by a fire safety engineering analysis conducted by a qualified fire safety engineer to demonstrate that fire or smoke will not spread between them.

    Additionally, 120-minute fire compartmentation (EI) or (ESa – doorsets) should be implemented to physically separate the generator from any adjacent fire risks, whether located at the ground floor or roof level.

    Fire-Resistant Cable Routing & Protection

    • Category 1 – 30 minutes, means of escape applications
    • Category 2 – 60 minutes, means of escape: evacuation lift supplies, means-of-escape smoke control
    • Category 3 – 120 minutes, fire-fighting: firefighters lift supplies, sprinkler and wet riser pumps, fire-fighting smoke control (including any firefighter override)

     

    Fire alarm circuits follow BS 5839-1 rather than this category list. The application-by-application assignment is BS 8519:2020 Table 1.

    • Dedicated Cable Support Systems: Cables for life safety systems must have dedicated supports rated for the same fire survival time.
    • Fire-fighting applications (firefighters lift supplies, sprinkler and wet riser pumps, fire-fighting smoke control) are Category 3, 120 minutes. [BS 8519:2020, Table 1]
    • Category 3 fire-resistant control cables must be installed between each ATS and the generator to transmit the start signal and status indication in case of a supply failure. In areas prone to mechanical damage, unprotected fire-resistant control cables should be additionally protected by using armoured cables or enclosing them within a cable tray with a lid.

     

    • Cables in protected escape routes: only cables meeting Regulation 422.2.1 may be installed there (limited smoke production with 60% light transmittance to BS EN 61034-2, halogen acid gas not exceeding 0.5% to BS EN 60754-1, and flame propagation to the BS EN 60332-3 series or BS EN 60332-1-2 as applicable); cable management systems must be classified non-flame propagating to their product standard (BS EN 61386 conduit, BS EN 50085 trunking and ducting, BS EN 61537 tray and ladder). Cables in a fire-resisting enclosure rated not less than the compartment, or as specified by the fire engineer, are deemed outside the route. [BS 7671:2018+A4:2026, 422.2.1 and 422.2.202]
    • Fire-Stopping: Any cable penetrations in fire-rated barriers must be sealed with fire-resistant materials per BS 8519.
    • Cable support systems for fire-resistant and non-fire-resistant cables should be kept separate. When running along the same route, the fire-resistant cable support system should, where feasible, be installed above the non-fire-resistant system. [BS 8519:2020. 16]
    • For further guidance, refer to Wiring in Protected Escape Routes.

    Fuel Storage & Containment

    A local fuel service tank should be provided within the generator building fabric enclosure large enough for at least 120 min of operation at rated power, including the appropriate bunding to protect against the risk of a fuel leak.

    However, the minimum Fuel storage capacity shall be based on BS EN 12101-10:2005. Therefore, additional fuel storage may be required if the ‘day tank’ capacity is less than shown in the table minimum fuel storage requirements for life safety generators.

    • Pipe-in-Pipe Systems: Use Brugg Pipe-in-Pipe or equivalent double-containment system.
    • Vacuum Leak Detection: SGB System recommended.
    • Thermal Shut-off Valve: Stops fuel flow in case of fire.
    • Fuel Dump System: Emergency drainage mechanism.
    • Alternative Systems: Durapipe PLX, KPS OPW.

    Location & Fire Compartmentation

    To protect against fire and structural failures, BS 8519:2020 recommends:

    • Generators should be housed in a dedicated plant room with 120-minute fire separation. 
    • Switchrooms and distribution boards must be fire-protected and separated from other services. The same rules are introduced in (Table 4 of BS 9991:2024 based on building height) this is also stated in BS 9999 – in practice, it means a requirement for 120-minute fire separation for generator housing.
    • If both primary and secondary power sources are on the ground or roof level, they must be enclosed separately to prevent fire spread. (Requirement for 120-minute fire separation of roof slab)

    Parallel Operation of Generators

    Paralleling generator systems offers substantial reliability and redundancy advantages, especially with an N+1 configuration. 

    Earthing Considerations

    Earthing Considerations for Life Safety Generators in TN-S Systems

    In the UK, TN-S earthing is the most common system, and integrating a life-safety generator into such a system requires careful planning to ensure fault clearance and safety.

    TN-S System Approach
    • Single Neutral-Earth Bonding: Ensure that the neutral-to-earth bond exists only at one location, typically at the main LV switchboard, not at the generator.
    • Generator Frame Earthing: The generator frame should be earthed to the Main Earth Terminal (MET) using a suitably rated conductor, while ensuring it does not create a second neutral-earth bond.
    • Avoid Neutral Bonding Conflicts: If the generator creates an additional neutral-to-earth bond while being connected to a TN-S system, it can lead to parallel paths, circulating currents, and malfunctions of protective devices.
    • Selective Fault Protection: The generator’s lower short-circuit current must be accounted for when setting earth fault protection to ensure timely disconnection of faults.
    IT Earthing for Life Safety Generators

    For life-safety generators, an IT earthing configuration is often preferred to enhance resilience. The following strategies should be considered:

    • Neutral Separation at the ATS: The generator’s neutral must be isolated from the building’s TN-S neutral to prevent unintended parallel paths. This is typically achieved by using a four-pole Automatic Transfer Switch (ATS), which switches the neutral along with the phases.
    • High-Impedance Neutral Earthing Resistor (NER): Instead of solid earthing, a high-impedance NER can be installed to limit earth fault currents, reducing damage risk and improving system stability.
    • Insulation Monitoring Devices (IMDs): Since an IT system does not provide a low-impedance path for earth faults, an IMD continuously monitors insulation resistance. If a first fault occurs, it alerts maintenance personnel without disconnecting power, ensuring continuity for life-safety loads.
    • Selective Earth Fault Protection: Protection settings must be adjusted to ensure earth fault detection is effective while avoiding miscoordination between the TN-S system and the generator’s IT earthing.
    • Integration with Fire Strategy & Compliance: Any modifications to the earthing scheme must align with BS 7671:2018+A4:2026 wiring regulations and BS 9999 fire strategy.

    Selective Fault Protection & Earth Fault Clearance

    One of the key challenges with life safety generators is ensuring that earth faults are cleared effectively despite the generator’s lower short-circuit current capability. The following measures help prevent faults from going undetected or protection devices failing to trip in time:

    • Adjusting Earth Fault Protection Sensitivity: Standard protection settings used for grid supply may not work correctly with a generator. Lower trip thresholds and time-delayed responses should be used to account for the reduced short-circuit current.
    • Ensuring Adequate Disconnection Times: BS 7671:2018+A4:2026 specifies maximum allowable disconnection times for protective devices. These must be verified against the generator’s fault current output, ensuring that protective devices trip within required timescales.
    • Using Residual Current Devices (RCDs) Where Necessary: In cases where low fault current may not be enough to trip conventional overcurrent protection, RCDs with appropriate settings can be used to ensure faults are detected and cleared. (RCD protection is not recommended for life safety systems.)
    • Neutral-Earth Bonding Considerations: If the generator neutral is not bonded correctly or an incorrect earthing scheme is used, fault protection may not function as expected. Careful coordination is required between generator earthing and main MET connections.

    Final Design Validation

    The standby generator should be capable of providing the supply to the critical life safety and fire-fighting load within 15 s of the failure of the primary supply in accordance with BS 9999 and BS EN 12845.

    Sample Cause-and-Effect Matrix 

    This table follows the chronological sequence of power failure, generator startup, and emergency load activation.

    Load Activation & Interlocking (After Power Transfer)

    Once the generator is running and loads are transferred, life-safety systems activate in a controlled sequence to prevent overload.

    Key Takeaways:

    • Sequencing prevents simultaneous high-inrush loads.
    • Fire systems activated only in affected zones, reduce generator load.

    The record BS 7671 requires you to produce

    Reg 560.7.11: a list of all the current-using equipment permanently connected to the safety power supply, indicating the nominal electrical power, rated nominal voltage, current and starting current, together with its duration. That list is your sizing study, formalised, and it is what building control and the insurer ask to see. The Generator Load Calculator generates it automatically from the loads you enter.

    Online Generator Load Calculator - Do this in minutes!

    The Generator Load Calculator runs everything on this page: pick your loads from a typical library or enter your own, and it builds the time-step profile with the TB210 worst case as the default, applies the BS 9999 15 second timebase, states the G2 acceptance criteria and recommends the standby set. Free to run, no signup, every figure traceable to the clause it came from.

    The Engineering Toolkit (79 GBP a year) turns it into a report, with a Reg 560.7.11 equipment record and secondary-supply schematic in editable Word and Excel, the sequential start advisor that helps to reduce the Gen size, the fuel and endurance check, and reports saved to your projects. The same subscription covers the cable tray and duct sizing calculators, so the generator you size here can have a compliant tray and duct route.

    Generator Maintenance & System Testing

    Ensuring long-term reliability involves routine testing and load assessments:

    • Weekly: Test ATS functionality & check fuel levels.
    • Periodic on-load testing to the set manufacturer’s regime (BS 8519:2020 sets no interval); load bank testing where building load cannot exercise the set.
    • Annually: Simulate a full-scale power failure test.
    • Every 3 years: Review fuel quality & replace if necessary to prevent degradation.
    On This page

      Leave a Reply

      Your email address will not be published. Required fields are marked *

      share this page